Do civilized construction, municipal Tiejun in action!
The publisher:czszjs    Release time:2017-09-27    Hit:12227

 In Changzhou the first water depth treatment project construction process, the construction site near the residential area, so the civilized construction is particularly important, Changzhou municipal scientific arrangement, balanced, and always will be the civilization construction in a prominent position.

In the project, the pit depth of the sludge treatment pool has been over 5 meters, and only 2 meters away from the foundation pit. After two expert demonstrations, the support of the foundation pit changed to continuous bored pile support.
Bored pile total 142, the planned construction period for 12 days, the project department in order to try not to affect the surrounding residents normal rest, the initiative will be the construction time schedule in the morning 7 points to 11 points, at 1 points to 5 points, the construction time is extended to 36 days, a day on average only 4 supporting construction pile, thus truly hard construction, civilized construction is not a nuisance.
A day before the construction project Department of civilized construction for construction personnel work, enhance the construction of the whole staff to prevent man-made noise nuisance consciousness; the project department person, time increase watering on the construction area of the vehicle washing density, to prevent dust pollution affect the lives of the residents, so the good intentions of civilized construction.
In the process of construction, material transport vehicles through the damaged pavement will make great noise, a greater impact on the rest of the residents, so the project department repeated testing, laying straw between iron and road, and then guide the driver through the low speed, so as to effectively reduce environmental noise. In addition, if encountered due to technical reasons, it can not be avoided, continuous construction at night when the project will advance around the work of the masses, and report the site posted a notice to reassure the public, the District Environmental Protection Bureau for the record after the construction, so as to make people close friends.
Do the civilized construction measures at the same time, the project department has also set up the surrounding residents visiting the reception room, and regular visits to the surrounding residents, listen to opinions and suggestions on the construction of the environmental protection field of residents, made surrounding residents understanding and support, thus make people feel comfortable in the construction process.
 
 

Print this page || Close the window

Jiangsu province Changzhou City Blue Ocean 158 North Road| Zip code:213017 | Telephone:0086-0519-85501558 | Fax:0086-0519-85501558 | E-mail:czsz@czszjt.com

Copyright © CHANGZHOU MUNICIPAL ADMINISTRATION CONSTRUCTION ENGINEERING CO.,LTD.  蘇ICP備12078434號(hào)-1   Technical support:Public science and technology